General information |
|
|
Name |
IN OPERATION? Amal I
|
|
Country installed |
Oman
|
|
Address |
Amal, Oman
|
|
Industry sector, NACE code |
B - Mining and quarrying
|
|
Solar thermal system owner / operator |
|
|
Solar thermal engineering company |
GlassPoint
|
|
Process integration engineering company |
|
|
Year of operation start |
2012
|
|
|
Technical parameters |
|
|
Collector technology |
parabolic trough collector
|
|
Collector name |
GlassPoint Enclosed Trough
|
|
Installed collector area (gross), m² |
17280.0
|
|
Installed collector area (aperture), m² |
|
|
Installed collector area (absorber), m² |
|
|
Installed thermal power (actual), kWth |
9000.0
|
|
Solar collector loop heat transfer fluid |
|
|
Solar energy storage |
no solar energy storage
|
|
Storage volume, m³ |
|
|
Kind of conventional heat source |
|
|
Kind of fuel used |
natural gas
|
|
|
Process |
|
|
Solar thermal energy used for |
steam generation
|
|
Unit operation |
extraction
|
|
Point of Solar Heat Integration |
B1) Heating of process(es) / process vessel(s)
|
|
--> Integration how and where |
|
|
--> Temperature range process |
|
|
--> Temperature range solar loop (min/max), C° |
|
|
|
Economic parameters |
|
|
Total investment costs (excl. VAT), € |
1.00
(Turnkey costs including solar collectors, piping, support construction, storage, design, commissioning reduced with subsidies)
|
|
Solar loop (excl. VAT), € |
(Solar collectors, piping, support construction)
|
|
Solar energy storage (excl. VAT), € |
|
|
Others (excl. VAT), € |
(Design, commissioning, others)
|
|
Process integration (excl. VAT), € |
|
|
Subsidy, € or % of total investment costs |
not known
|
|
Cost for fuel replaced, €/MWhfuel |
|
|
Calculated solar thermal system life time, a |
|
|
Annual useful solar heat delivery, MWh/a |
12000
|
|
Specific annual useful solar heat delivery, MWh/am² |
0.69
|
|
Specific investment costs, €/m² |
0.0
|
|
Solar fraction, % |
|
|
|
Lessons learned |
|
|
Initiative |
|
|
Integration methodology |
|
|
Crucial Interfaces |
|
|
Construction / Commissioning |
|
|
Operation / Performance |
|
|
Recommendations |
|
|
|
Source |
|
|
Author |
Jasmin Pfleger via GlassPoint
|
|
Company of author |
AEE INTEC
|
|
E-mail |
j.pfleger@aee.at
|
|
Phone |
|
|
Homepage |
https://www.glasspoint.com/
|
|
|
|
|
|
|
|
|
|